newmta.info

Capital Program 2005–2009

Eye on the Future: Information about contracts that should be advertised by the Metropolitan Transportation Authority from January to June 2009 for professional services, construction, and equipment procurement.

Introduction

In April 2005, the MTA Board approved a revised 2005-2009 Capital Program totaling $21.145 billion reflecting legislative actions taken in response to the MTA's original 2005-2009 plan proposal submitted to the CPRB in October 2004. Transit and commuter portions of this plan totaling $17.987 billion were submitted to the CPRB and approved with minor program modifications in July 2005.

The amendment presented herein adjusts the approved capital program as shown on Table I to include federal earmarks, reflect new MTA bus funding as a result of MTA's takeover of private buses, and update project scopes, schedules and budgets. The revised five-year program proposed herein now totals $21.285 billion.

Table I
2005-2009 Capital Program Amendment
($ in millions)

Program Elements

CPRB Approved Plan

Proposed Plan

Change

Core Capital Programs

 

 

 

New York City Transit

$11,300.1

$11,301.1

$1.0

Long Island Rail Road

2,176.0

2,176.0

$0.0

Metro-North Railroad

1,382.3

1,383.1

$0.8

CPRB Core Subtotal

$14,858.4

$14,860.2

$1.8

Security Program

495.0

495.0

0.0

Interagency

159.1

159.1

0.0

Core and Security Subtotal

$15,512.4

$15,514.2

$1.8

ESA/SAS/JFK Link

2,475.0

2,475.0

0.0

Total 2005-2009 CPRB Program

$17,987.4

$17,989.2

$1.8

City #7 Line Extension

1,990.0

1,990.0

0.0

Bridges and Tunnels

1,167.9

1,167.9

0.0

MTA Bus

0.0

138.2

$138.2

Total 2005-2009 Capital Program

$21,145.3

$21,285.3

$140.0

The overall increase to the program is primarily due to the addition of $138 million of federal and matching funds to the MTA Bus Company capital program. New federal earmarks and other dedicated federal funding have resulted in a modest increase to the CPRB based program. Within the agency programs some notable changes have occurred; cost increases and programmatic adjustments have necessitated some project deferrals. These are discussed in the following agency narratives.

Availability of Funding

The overall program size remains has increased by $140 million, as shown in Table II, reflecting changes in the fund sources highlighted on the table and as described in the following narrative.

Table II
2005-2009 MTA Capital Program Funding Sources
($ in millions)

Funding Source

CPRB Approved Plan

Proposed Plan

Change

Federal Formula and Flexible

$5,093.0

$5,221.2

$128.2

Federal New Start

1,000.0

1,000.0

0.0

Federal Security

495.0

495.00

0.0

City

400.0

400.0

0.0

City #7 Line Funds

1,990.0

1,990.0

0.0

City Match for Buses

0.0

27.6

27.6

Asset Sales/Program Income/Carryover

1,400.0

1,384.2

(15.8)

Bond Act

1,450.0

1,450.0

0.0

MTA Bonds (including B&T)

4,217.3

4,217.3

0.0

MTA Bonds New Source

5,100.0

5,100.0

0.0

Total 2005-2009 Capital Program

$21,145.3

$21,285.3

$140.0

Less # 7 Line Extension

($1,990.0)

($1,990.0)

$0.0

Less Bridges and Tunnels

($1,167.9)

($1,167.9)

$0.0

Less MTA Bus

$0.0

(138.2)

($138.2)

Total 2005-2009 CPRB Program

$17,987.4

$17,989.2

$1.8

Federal Formula and Flexible $128.2 million

Due to the merger of the New York City private bus companies into the MTA there will be additional formula funds available for MTA Bus. These funds are estimated at $110.6 million from 2006-2009. In addition, MTA received two new federal earmarks: $4 million for New York City Transit's (NYCT) Bay Ridge 86 th St. Station (a new project), $0.4 million for NYCT's Myrtle/Wyckoff Transit hub (existing project), and $0.8 million for NYCT's Bus Rapid Transit study (existing project). Westchester County transferred $12 million of federal funds to the MTA for the installation of MetroCard fareboxes in Westchester County buses (Bee-Line), and New York State DOT allocated $0.4 million of federal funds to the MTA for a Metro-North Railroad (MNR) project in Croton.

City/State Match For Buses $27.6 million

The City will match the additional federal formula funds that MTA is receiving for the MTA Bus Company by drawing down a 10 percent match from the State and providing their local 10 percent match for a total of a 20 percent match to the federal funds. The total estimated match for 2006-2009 is $27.6 million.

Asset Sales/Program Income/Carryover ($15.8 million)

The decrease to this funding category results primarily from the transfer of $15 million of capital funding from the 2005-2009 NYCT Capital Program back to the 2000-2004 NYCT Capital Program to consolidate all project funding for the construction of the new Staten Island Charleston Depot in the 2000-2004 Capital Program.

 

DISCUSSION OF AGENCY PROGRAMS

MTA New York City Transit

NYC Transit's revised 2005-2009 Capital Program is $11.301 billion, an increase of $1 million from the approved level of $11.300 billion. The increase in the overall budget reflects $12.0 million of federal funds from Westchester County for the purchase of fareboxes for the BeeLine and a $4.0 million federal earmark for station improvements at the 86 th St. station Brooklyn . Offsetting these additions is the transfer of $15.0 million to the 2000-2004 Capital Program for the Staten Island ( Charleston ) depot project. NYCT's proposed amendment adjusts project budgets throughout the program to reflect refined scopes, cost estimates, bid experience, and schedule changes since the last update to the Board. Table III summarizes the proposed changes by category and the following narrative highlights the major changes in each of NYCT's program areas.

Table III
MTA New York City Transit 2005-2009 Capital Program by Investment Category
($ in millions)

    Category CPRB Approved Plan   Proposed Plan     Change

Subway Cars

$1,805

$1,805

$0

Buses

824

834

10

Passenger Stations

1,686

1,655

(31)

Track

1,138

1,142

4

Line Equipment

977

963

(14)

Line Structures

616

627

11

Signals and Communications

1,844

1,882

39

Power

553

585

32

Shops

271

290

19

Yards

350

272

(78)

Depots

636

613

(23)

Service Vehicles

99

114

15

Miscellaneous

416

434

18

Staten Island Railway

86

86

0

New York City Transit Total

$11,300

$11,301

$1

New Cars No Change

There is no change in the subway car purchase category. The plan includes the normal replacement of 912 B Division cars and fleet growth for the A Division with the purchase of 47 cars.

Buses $10 million

The increase in this category mainly reflects the addition of $12.0 million for the procurement of fareboxes for the Westchester Bee-Line, the bus service in Westchester County . NYC Transit is procuring the units via an existing contract with its farebox manufacturer on behalf of the Bee-Line, and will be reimbursed by Westchester County for all expenses. This was approved by the Board in October 2005.

The overall bus purchase program remains the same, though the schedules of certain purchases have been adjusted. A total of 1,360 new buses will be ordered, including 1,010 standard (all using clean fuel technology), 112 articulated, and 238 express buses. The new bus purchases represent a fleet growth of approximately four percent in "standard bus equivalents" (SBEs) over the current fleet. In addition, 948 new paratransit vehicles will be purchased to replace older units and to expand the total fleet by approximately 33 percent. Other bus-related investments include the replacement of ticket processing units and coin modules on all NYCT Integrated Farebox Units and research to reduce bus emissions.

Passenger Stations ( $31 million)

The decrease in this category primarily reflects the deferral of most of the Times Square Shuttle reconstruction project. A portion of it remains in the program to improve and add new entrances on the northern side of the Times Square station complex in coordination with NYCDOT plans to reconfigure sidewalks in the Times Square area. In addition, the project to make only key repairs at the Smith-9 th St. station in Brooklyn has been restored to a comprehensive station rehabilitation. Thus, NYCT's plan continues to fund the rehabilitation of 44 stations. Favorable bids on the Columbus Circle project also contributed to the reduction in this category's budget.

Several projects are added to the category, including: the initial phase to retrofit station gates with emergency release bars ($15.0 million); a station condition survey ($3.0 million); platform / canopy improvements at the Dyckman St. station on the Broadway/7 th Ave. line ($9.8 million); normal replacement improvements at the Pelham Bay Park station on the Pelham line ($3.8 million); improvements to the 86 th St. station on the 4 th Ave. line ($4.0 million through a federal earmark); and additional high entry/exit turnstiles to be installed via station rehabilitation projects ($1.5 million). Also, design funds ($7.5 million) are transferred from the program-wide design reserve to the rehabilitation / ADA projects at ten stations on the West End line. The condition survey, the Pelham Bay Park work and the West End line station designs previously were funded in the 2000-2004 Capital Program. The rest of the Stations category is largely unchanged and still funds full accessibility / ADA investments at 17 key stations, replacement of 25 escalators at four stations, and new passenger transfers at Bleecker St. in Manhattan and Jay St. in Brooklyn .

Track $4 million

A $5.0 million increase in the 2005 mainline track replacement project is the main change in this category to better address program support costs. The program funds normal replacement of approximately 49 miles of mainline track and 177 mainline switches. The largest share of work is panel track installed in prefabricated sections on elevated and open-cut/at-grade structures. The remaining track work is in the subway where a concrete invert is poured with embedded ties. The number of switches is reduced from 180 to 177; two switches are transferred to the Culver Viaduct repair project and a third was deferred due to bus G.O. scheduling issues. The program includes installation of 50 track miles of welded rail, which is expected to significantly lower occurrences of rail breaks and cracks.

Line Equipment ($14 million)

Project repackaging in tunnel lighting and budget increases in the vent and pump areas combine for the net decrease in this category's budget. The tunnel lighting program decreases by $34.9 million, mainly reflecting two projects. For efficiency, the scope of the Carroll St. – Cranberry Junction project was redistributed among other tunnel lighting projects in this program and the 2000-2004 program, and so this project no longer needs to be carried in this program. Also, the Times Square Shuttle project is deferred to coincide with the deferral of the Shuttle station reconstruction. The program now funds replacement of approximately 48 track miles of tunnel lighting, a reduction of five track miles from the approved plan.

The vent plant program increases by $11.9 million, mainly reflecting a higher estimate for the wrap-up project at Archer Ave. The scopes of two other projects are changed. The Astoria / QBL project originally was to replace in-kind three existing units and add one new unit. Instead, two existing plants will be replaced with a single larger unit and the third existing unit will be replaced in-kind. In turn, this eliminates the need for the new fan plant, saving $35.7 million while still meeting safety needs. The project to replace five fan plants on the 6 th Ave. line has been divided into two projects, one to replace two plants at 30 th St. and the other to replace two plants at other locations. Given their locations along a main thoroughfare in Manhattan , all locations are difficult construction sites requiring considerable utility relocation and additional cost. As a result, one location is deferred because its worksite is exceptionally difficult and its priority is low according to NYCT's earlier study of ventilation needs. Overall, the program changes from replacing 13 and adding four new fan plants to replacing 12 and adding three new fan plants.

The pump program increases by $9.2 million, reflecting a high bid on the Queens Boulevard Line project and the transfer of the rehabilitation of one other pump room from the 2000-2004 Capital Program. Work on this pump room, located in Lower Manhattan along the 8 th Ave. line at Fulton St. , was delayed due to the attack on the World Trade Center and the subsequent repairs occurring in the area. This program now funds s tate of good repair work at 17 pump rooms (an increase of one) on four lines and deep well normal replacement work to control water tables on three lines.

Line Structures $11 million

The increase in this category mainly reflects the addition of a project to install intrusion detection alarms at emergency exits throughout the system, a high bid on a painting project, and revised estimates for two other projects. There are no other significant changes in the category. Various line structure repairs, painting, and related work are addressed, including:

  • 9.0 route miles of subway structures on four lines: Joralemon Tube, 8 th Ave. , BMT Broadway, and Nassau .
  • 8.0 route miles of elevated structure on the West End line and the Culver, Ocean Parkway , Rockaway, and Far Rockaway and Rockaway Park viaducts.
  • 3.8 route miles of retaining walls and overpasses on the at-grade Sea Beach line.
  • Painting projects on the Jerome, White Plains Road , Pelham , Jamaica , Rockaway, Broadway-7 th Ave. , Flushing, Culver, and Astoria lines.
  • Rehabilitation of 125 emergency exits throughout the subway system.

Signals and Communications $39 million

The net increase in this category results from scope and budget increases in several projects. In the signals area, an increase in the Chambers interlocking scope of work has been offset by the deferral of other interlocking work on the Crosstown Line. The scope of the Chambers St. Interlocking project is expanded to address two more interlockings for a total of three on the 8 th Ave. line to achieve greater project implementation efficiencies and to reduce the long-term impact on service. In addition, the Stop Cable Replacement budget has experienced increases in unit costs. In the communication systems area the mix of projects remains unchanged though the budgets of two projects have notable increases. The Antenna Cable Replacement-Phase 2 project increases by $13.7 million, reflecting completion of project master plan as well as the experience gained in Phase 1 (funded in the 2000-2004 program). The Data Network Phase 2 budget has increased by $46.8 million due to higher contract and in-house costs. As an option to an ongoing contract, this is the final step in extending NYCT's fiber optic network to all stations and ultimately providing improved service announcements.

Power $32 million

This category's increase mainly reflects higher estimates for a transformer replacement project and the Rockwell Place Substation project, bid experience for several recently awarded substation modernization projects, and the transfer of a project for miscellaneous repairs at various substation enclosures ($13.6 million) from the 2000-2004 Capital Program. The budget for a control cables project is reduced by $14.2 million, reflecting a lower revised estimate. The work in this category generally remains unchanged and includes modernizing nine substations, rehabilitating three IRT and three IND substation enclosures, replacing substation equipment at various locations, rehabilitating eight circuit breaker houses, and other improvements to the power distribution system.

Shops $19 million

The increase in the category is due to two new projects and the increase in a third project budget. The first new project is the roof replacement at the 207 th St. Overhaul Shop ($15 million). Though budgeted separately, the roof will be addressed as part of the general rehabilitation of the overhaul shop. The second project -- an overhead crane ($1.5 million) at the Pitkin Shop -- is added to support maintenance of new technology subway cars. The budget for the 38 th St. Yard Shop project increases due to a high bid. The remainder of this category is unchanged.

Yards ($78 million)

The decrease in this category mainly reflects the reduction of the Jamaica Yard Expansion project; a portion of it ($20.0 million) remains funded for design and initial work. Completed project master plans result in increased budgets for the 38 th St Yard Viaduct and the Yard Fencing Upgrade projects. Also, a project is added to survey and design improvements to yard perimeter security systems. There are no changes to the yard track and switch budgets. The program will replace approximately seven miles of yard and non-revenue track and replace 100 yard switches.

Depots ($23 million)

The principal change in the category is the transfer of $15.0 million for the new Charleston Depot on Staten Island from this program to the 2000-2004 Capital Program. This and other budget actions related to Charleston (discussed in the December 2005 amendment to the 2000-2004 Capital Program) combine to fully fund the depot project in the 2000-2004 Capital Program. In addition, budgets for several small depot improvement projects are lowered, reflecting favorable bids and revised engineering estimates. The remainder of the category remains unchanged.

Service Vehicles $15 million

The increase in this category reflects the bid experience to purchase a total of 28 locomotives. The contract was awarded in 2005 with 9 units funded in the 2000-2004 Capital Program and 19 in the 2005-2009 Capital Program. The rest of the category is unchanged. The program will replace a total of 212 heavy-duty rubber-tire vehicles and 22 work train vehicles.

 

Miscellaneous $18 million

This category includes funds to support the overall program, including program contingency, insurance, engineering and environmental services, and scope-development. In addition, improvements to employee facilities across the system as well as certain management information systems are funded in this category. The increase in the category primarily is due to the addition of a project for the purchase of the Tiffany St. Warehouse, which currently is leased. Ultimately, this facility will be upgraded through future capital projects to replace NYCT's existing central warehouse in Queens . Program contingency is added to address unforeseen needs.

Staten Island Railway No change

There are no changes to report in the category.


Elements Exceeding 10 Percent of the Approved Plan

In the proposed capital program amendment, the budgets in certain 2005-2009 Capital Program elements are greater than the 10 percent margin allowed by the Public Authorities Law without approval by the Capital Program Review Board (CPRB). These "10 percent" items are shown in Table IV. These items will require CPRB approval in order to progress at the proposed plan funding levels.

Table IV
NYC Transit Elements with Increases Exceeding 10 Percent
($ in millions)

  Element

CPRB Approved Plan

  Proposed Plan

Change

Communications Systems

$419

$477

$58

Substations

$243

$282

$40

Service Vehicles

$99

$114

$15

Employee Facilities

$114

$127

$15

MTA Long Island Rail Road

The Long Island Rail Road (LIRR) 2005-2009 Capital Program total remains unchanged at $2.176 billion.

In this amendment, several projects are added, including the initial phase of the rehabilitation of the Atlantic Avenue Viaduct. Additional funds are needed for increased M-7 delivery costs and cost increases to the signals program. Budget adjustments are also made to account for an increase in overhead costs affecting projects with in-house labor components. To offset these increases, the LIRR will defer the rehabilitation of Hunterspoint Avenue Station, signal improvements at Jay and Hall Interlockings and design/property acquisition for a new mid-Suffolk yard to the next capital program. The concrete tie program is also deferred to help fund other priority needs without impact on track state of good repair.

Table V and the discussion following summarize the proposed changes to the LIRR 2005-2009 Capital Program by investment category.  

Table V
LIRR 2005-2009 Capital Program by Category
($ in millions)

  Category

CPRB
Approved Plan

Proposed
Plan

  Change

Rolling Stock

$359

$376

$ 17

Passenger Stations

135

114

(21)

Track

726

637

(89)

Line Structures

156

251

9 5

Communications & Signals

347

363

16

Shops & Yards

111

108

(3)

Power

159

145

(14)

Miscellaneous

185

183

(2)

Long Island Rail Road Total

$2,176

$ 2,176

$ 0

Rolling Stock $17 million

The rolling stock investment for the LIRR electric fleet includes the purchase of 158 new M-7 electric cars, continuing the normal life cycle replacement of M-1 electric multiple units nearing the end of their useful life. Capital funding is reprogrammed to support M-7 project budget adjustments – reflecting minor scope changes as well as rising escalation costs due to adjustments in economic indices and increased material costs, most notably steel ($19 million). The M-9 specification development project has been deferred to help support this need ($2 million).

Passenger Stations ( $21 million)

Station investments include platform rehabilitations, replacement of stairs, escalators, elevators and overpasses at locations system-wide and the construction/rehabilitation of parking spaces. Also included is the purchase and installation of up to 87 ticket vending machines (TVMs) for stations throughout the system, expanding the number already in service. The rehabilitation of the Hunterspoint Avenue Station in Queens and the design of the coordinated signage initiative with Amtrak and New Jersey Transit at Penn Station are deferred, and the budget for some infrastructure work in Penn Station is reduced.

Track ($89 million)

The ongoing track rehabilitation work consists of the normal replacement of track components. Also included is phase one of design and construction of grade crossing eliminations and track capacity improvements on the Main Line from Queens Village to Hicksville. The annual track programs are being reduced to reflect the deferral of the concrete tie work to help fund increases in other areas. State of good repair of the track network is not affected by this deferral. Also, a project for direct track fixation work on the Babylon Branch (at Amityville, Copiague and Lindenhurst ) and a project to rehabilitate Amott culvert are added.

The initial construction phase for the reconfiguration of Jay Interlocking is deferred to the next capital program, in coordination with revisions to the Signals program (discussed below). A portion of the project to double track the Main Line from Farmingdale to Ronkonkoma (design and property acquisition) is also deferred. The EIS will, however, be progressed.

Line Structures $95 million

Investments in line structures consist of the rehabilitation of bridges and viaducts. A $78 million project for the first phase of the rehabilitation of the Atlantic Avenue Viaduct is added to the program. (The viaduct is used for service between Jamaica and Atlantic Terminal.) Several smaller bridge projects are broken out from the base bridge rehabilitation program.

Work on the East River Tunnel fire and life safety project also continues, though the budget increases to incorporate additional testing and control features.

Communications and Signals $16 million

LIRR's communications investments include the continued expansion of the fiber optic network and redesign of the communication network operations center. LIRR's VHF radio system will be modernized and Audio/Visual Paging systems (AVPS) will be deployed at 80 additional stations. The LIRR will continue its normal replacement of deteriorated communications poles system-wide.

Signal projects rehabilitate interlockings, invest in signals as far east as Speonk, begin work on the centralized train control system and continue cyclical normal replacement. The budgets for the signal program reflect revised estimates-to-complete. Construction for the Jay and Hall Interlocking projects is deferred although design remains and will be progressed under a separate project. A portion of the Babylon to Patchogue project is also deferred to the next capital program.

Shops and Yards ($3 million)

Investments in shops and yards include the replacement of rolling stock support equipment, infrastructure improvements to accommodate maintenance and repair of the new electric diesel fleets, soil remediation at Long Island City yard and reconfiguration of Babylon yard to increase lay-up storage capacity. The project to reconfigure shops to support Life Cycle Maintenance (LCM) is now split into two projects: one project for construction of a new HVAC shop and a second project for LCM design/construction at remaining locations system-wide. A new project is added to upgrade LIRR's diesel locomotive shops, including replacement of the turntable at Morris Park ($9 million). This plan defers $14.1 million for the Mid-Suffolk Yard design and property acquisition into the next plan.

Power ($14 million)

The power category includes the replacement and upgrade of the systems necessary to support the movement of electric trains. The budget for the power system upgrade project has been reduced, deferring some of the initiatives to increase the supply of traction power to help fund increases in other areas.

Miscellaneous ($2 million)

This category of investment includes various program administrative costs, including program contingency. Program Development (designs for future capital program work) and Program Administration (administrative costs to manage the capital program) are reduced slightly.


Elements Exceeding 10 Percent of the Approved Plan

In the proposed capital program amendment, the budgets in certain 2005-2009 Capital Program elements are greater than the 10 percent margin allowed by the Public Authorities Law without approval by the Capital Program Review Board (CPRB). These "10 percent" items are shown in Table VI. These items will require CPRB approval in order to progress at the proposed plan funding levels.  

Table VI
LIRR Elements with Increases Exceeding 10 Percent
($ in millions)

  Element

CPRB Approved Plan

Proposed Plan

  Change

Bridges

$86.3

$160.2

$73.9

Tunnels

$69.7

$90.5

$20.8

Numbers may not total due to rounding

 

Metro-North Railroad  

The MNR 2005-2009 Capital Program total increases to $1.383 billion.

In this amendment, MNR eliminates the $128 million project to overhaul 140 M-3 electric cars. Instead, MNR will increase ongoing maintenance levels for the M-3's to be funded by its operating budget. Funds made available by this action help fund cost increases in the program for the M-7 car deliveries and the Harmon Shop Master Plan.

Table VII and the discussion following summarize the proposed changes to the MNR 2005-2009 Capital Program by investment category.  

Table VII
MNR 2005-2009 Capital Program by Category
($ in millions)

  Category

CPRB Approved Plan

Proposed Plan

Change

Rolling Stock

$364

$284

($80)

Stations

238

234

(5)

Track and Structures

256

256

0

Communications and Signals

73

73

0

Power

103

103

0

Shops and Yards

260

340

80

Miscellaneous

88

93

5

Metro-North Railroad Total

$1,382

$1,383

$1

                Numbers may not total due to rounding

Rolling Stock ($80 million)

MNR investments in this area continue the modernization of the fleet with the completion of the M-2 overhaul, the purchase of 100 M-8 electric cars to begin the replacement of the New Haven Line's M-2 fleet (w/ CDOT) and the purchase of 36 M-7 electric cars to complete the replacement and expansion of the M-1 fleet.

MNR will forego an extensive capital remanufacture of the 140 car M-3 fleet in favor of maintaining the fleet at enhanced levels through the operating budget. This change avoids the high per car cost of a full remanufacture. Approximately one third of this capital funding is reprogrammed to fund M-7 project budget adjustments – reflecting minor scope changes, as well as rising escalation costs due to adjustments in economic indices and increased material costs, most notably steel ($47 million). A new project is also added to allow for the development of a specification for an M-3 replacement car, the M-9 ($1 million). The balance of the M-3 project budget is transferred to the Shops and Yards category to support needs there.

Passenger Stations ($ 5 million)

The stations category includes the continued structural rehabilitation of Grand Central Terminal, the rehabilitation of select stations on the Hudson , Harlem and New Haven Lines (in New York State ), the advancement of strategic intermodal station/parking facilities and expansion of parking facilities at locations system-wide. This category is reduced by $5 million as a result of a favorable bid and slight change in scope to the GCT Exterior Rehabilitation project. The remainder of this category remains unchanged.

Track and Structures No Change

The ongoing track program provides for replacement of ties and rail along with cyclical surfacing and interlocking/switch replacement throughout the entire MNR territory in New York State . It includes the repair of undergrade/overhead bridges throughout the territory, work on welfare, storage and other facilities and West of Hudson track improvements. This category remains unchanged from the current approved plan with one exception: The project for Bridge Preservation ($0.8 million) is deferred and the funding will be reallocated to the Beacon Line Bridge project.

Communications and Signals No Change

Investments in communications and signals replace the aging signal system with the latest technology and provide for the optimization of train capacity at locations system-wide. This category remains unchanged from the current approved plan.

Power No Change

Power investments maintain the condition of existing assets and increase traction power capacity system-wide. This category remains unchanged from the current approved plan.

Shops and Yards $80 million

The shops and yards investment for MNR include upgrades to three facilities to accommodate additions to the rolling stock fleet and support for the Reliability Centered Maintenance philosophy. Funds are transferred from the Rolling Stock category to fund significant cost increases in the ongoing Croton-Harmon Shop Master Plan ($81 million). In addition, the Harmon scope is expanded to fund critical needs for wheel truing, priority repairs, and utility upgrades for M-7 Shop equipment. Finally, the Highbridge Yard Car Wash project cost estimate has been increased to reflect refined estimates-to-complete ($3.6 million).

This plan defers $3 million from the rehabilitation and expansion of Brewster Yard and $3 million for miscellaneous building rehabilitations into the next plan.

Miscellaneous $5 million

This category of investment includes various program administrative costs, including program contingency. The $5 million increase is the result of the surplus funds moving from the Stations category into program contingency.

Elements Exceeding 10 Percent of the Approved Plan

In the proposed capital program amendment, the budgets in certain 2005-2009 Capital Program elements are greater than the 10 percent margin allowed by the Public Authorities Law without approval by the Capital Program Review Board (CPRB). These "10 percent" items are shown in Table VIII. These items will require CPRB approval in order to progress at the proposed plan funding levels.

Table VIII
MNR Elements with Increases Exceeding 10 Percent
($ in millions)

  Element

CPRB Approved Plan

Proposed Plan

Change

  Shops and Yards

$260

$340

$80

Numbers may not total due to rounding

 

MTA Bridges and Tunnels

The Bridges and Tunnels (B&T) 2005-2009 Capital Program total remains unchanged at $1.168 billion. Overall, the capital program objectives remain consistent with the approved plan. Approximately 91 percent of the program is allocated for the normal replacement of assets which have reached their expected useful life, including two major deck rehabilitation projects at the Bronx-Whitestone and Robert F. Kennedy bridges.

Table IX and the discussion following summarize the proposed changes to the B&T 2005-2009 Capital Program by investment category.

Table IX
MTA B&T 2005-2009 Capital Program by Category
($ in millions)

  Category

MTA Board Approved Plan

Proposed Plan

Change

Structures

$221

$190

($31)

Roadways & Decks

695

703

8

Toll Plazas

74

84

11

Utilities

17

25

7

Buildings & Sites

144

144

0

Miscellaneous

17

22

5

MTA B&T Total

$ 1,168

$ 1,168

$0

Numbers may not total due to rounding

Structures ($31 million)

The budget for the structures category decreases primarily due to the reallocation of program contingency to fund work elsewhere in the program and transfer of work at the Throgs Neck Bridge to two projects in the Roadways and Decks category. There were increases totaling $17 million to three projects, substructure and underwater repair at the Cross Bay Bridge , structural steel repairs at the Marine Parkway Bridge and anchorage rehabilitation and dehumidification at the Robert F. Kennedy Bridge .

Roadways and Decks $8 million

The budget for this category increases to reflect an increase in the estimate for the replacement of the lower level deck at the Henry Hudson Bridge and the transfer of work at the Throgs Neck Bridge from the Structures category. Offsetting these increases is a good bid for the deck replacement at the Randall's Island Junction of the Robert F. Kennedy Bridge .

Toll Plazas $11 million

Toll Plaza and Traffic Management investments include the replacement of the upper level toll plaza decks at the Henry Hudson bridge, design of a new toll plaza at the Bronx Whitestone Bridge and various ITS and Traffic Management/Safety System initiatives. A new project is added for the design of a new toll plaza at the Verrazano-Narrows Bridge .

Utilities $7 million

Projects in this category include the replacement, rehabilitation or upgrade of mechanical, electrical and lighting systems and tunnel ventilation equipment. The budget increase results mainly from the addition of fiber installation and cameras for CCTV at the Brooklyn Battery Tunnel Control Center . A new project is added for the rehabilitation and upgrade of the tunnel ventilation buildings' electrical system at the Queens Midtown Tunnel. Also, the design for the replacement of the supply fan house is deferred.

Buildings and Sites No Change

This category includes the construction of new buildings and shops to accommodate tenants that will be relocated as a result of the deck replacement projects at the Robert F. Kennedy Bridge , the continued rehabilitation of ventilation buildings at the Brooklyn-Battery Tunnel and the rehabilitation of the service building at the Queens Midtown Tunnel. A decision was made to expand the new service building on Randall's Island to include some of the relocated B&T employees, and the central shops and warehouse.

Miscellaneous $5 million

The budget for this category increases to reflect increased costs for the management of the capital program.


MTA Bus Company

The MTA Bus Company was established in 2004 to merge operations of seven private bus services that were operated under an agreement with the City of New York . Agreements for the merger of all the private bus lines into the MTA Bus Company are now complete, and the mergers are expected to be finished by the end of February 2006. When creating the MTA Bus Company, the Board also amended the 2000-2004 Capital Program to provide capital funding targeted for the replacement of overage buses previously operated by the private companies. Those purchases are now underway.

As part of the transition of the private bus operations from the City of New York to the MTA, the City and the MTA have agreed to a reallocation of federal urbanized formula funds that the City had received for the benefit of the private bus companies. This reallocation is expected to provide $138.2 million over the MTA 2005-2009 Capital Program , and is comprised of $110.6 million in federal funds and $27.6 million in City and State matching funds . Reflecting the anticipated availability of this new funding, a capital budget totaling $138.2 million now is proposed to be established for MTA Bus in the 2005-2009 Capital Program ( Table X). The funding will support investments to bring bus maintenance facilities up to a state of good repair, thereby ensuring efficient and economical maintenance practices as well as improving employee safety at the facilities. In addition, the need to replace heavy-duty, non-revenue vehicles will be addressed.

Table X
MTA Bus Company 2005-2009 Capital Program by Investment Category
($ in millions)  

Category

CPRB Approved Plan

Proposed Plan

Change

Bus Company Projects

$0

$138

$138

Total

$0

$138

$138

                Numbers may not total due to rounding

MTA Security

The value of the MTA 2005-2009 Capital Security Program total remains unchanged at $495 million. Security program objectives remain consistent with the approved plan.

Table XI
MTA Security 2005-2009 Capital Program by Category
($ in millions)

  Category

CPRB Approved Plan

Proposed

Plan

  Change

Vulnerability Assessment Projects

$478

$478

$0

Security Readiness Support Initiatives

17

17

0

MTA Security Total

$495

$495

$0

                Numbers may not total due to rounding

Vulnerability Assessment Projects No Change

The approved MTA 2005-2009 Capital Program allocated $478 million to fund priority security initiatives, expecting to secure funding from Homeland Security and other federal sources for these critical projects. The MTA has secured $33 million for 2005 from the Federal Office of Domestic Preparedness to help progress this program.

Security Readiness Support Initiatives No Change

This category remains unchanged from the current approved plan.

MTA Interagency:

Customer Service Projects

There is no change in this area of the program. Funds are included to support a broad range of smaller initiatives to enhance customer amenities and services throughout the MTA region.

Table XII
Customer Service Projects 2005-2009 Capital Program by Category
($ in millions)

Category CPRB Approved Plan Proposed Plan Change

Customer Service Projects

$50

$50

$0

Customer Service Project Total

$50

$50

$0

Numbers may not total due to rounding


MTA Interagency:

MTA Police Department

The MTA Police department (PD) 2005-2009 Capital Program total remains unchanged at $64 million. Overall, the capital program objectives remain consistent with the approved plan. There have been no changes to any of the projects in the Police capital program, as shown on Table XIII.

Table XIII
MTA Police Department 2005-2009 Capital Program by Category
($ in millions) 

  Category

CPRB Approved Plan

Proposed Plan

Change

Suffolk County District Office

$5

$5

$0

Nassau County District Office

1

1

0

K-9 Training Facility

2

2

0

Emergency Services Units

1

1

0

Public Safety Radio

45

45

0

Communications Center Backup

2

2

0

Integrated Incident Management

0

0

0

Access Control

1

1

0

Enhanced 911

2

2

0

Engineering/Consulting Services

2

2

0

Program Administration/Contingency

4

4

0

MTA Police Department Total

$64

$64

$0

                Numbers may not total due to rounding


MTA Interagency:

MTA Integrated Systems Initiative

The 2005-2009 Capital Program for Integrated Systems remains unchanged at $45 million. Overall, the capital program objectives remain consistent with the approved plan. Within this category a new project has been created to fund the design and implementation plan for the creation of an MTA-wide Shared Services organization.

Table XIV
MTA Integrated Systems Initiative 2005-2009 Capital Program by Category
($ in millions)

  Category

CPRB Approved Plan

Proposed Plan

Change

Integrated Systems

$45

$45

$0

Integrated Systems Total

$45

$45

$0

   Numbers may not total due to rounding

 

MTA Capital Construction Company

The MTA Capital Construction Company's (CCC) 2005-2009 Capital Program will focus on the following system expansion projects:

  • Construct East Side Access (ESA), which will bring Long Island Rail Road commuters into Grand Central Terminal, creating a terminal on Manhattan 's East Side to complement Penn Station on the West Side .
  • Construct the initial phase of Second Avenue Subway (SAS), which will relieve the pressure on New York City Transit's overcrowded Lexington Avenue Line and improve access to downtown Manhattan .
  • Design and construct a direct rail link between Lower Manhattan , Jamaica and JFK International Airport .
  • Construct an extension of New York City Transit's Flushing (#7) subway line (to be funded by the City of New York ) in coordination with plans to develop Manhattan 's Far West side.

The budget for the system expansion program remains at the approved level of $4.465 billion, funding the above projects and CCC administration costs. In November 2005, a $2.9 billion state-wide Transportation Bond Act was approved, from which MTA will receive $1.45 billion, including funding for the 2005-2009 phases of the system expansion projects. Discussions between the MTA, state, and the Federal Transit Administration (FTA) are now underway to finalize the federal new starts funding for ESA and SAS. The #7 Line Extension project, funded 100 percent by the City of New York , remains in the plan at its full $1.990 billion value. 

Table XV
MTA Capital Construction Company Capital Program by Category
($ in millions)

  Category

CPRB Approved Plan

Proposed Plan

  Change

ESA / SAS / JFK Link

$2,400

$2,400

$0

#7 Line Extension

1,990

1,990

0

CCC Administration

75

75

0

Capital Construction Company Total

$4,465

$4,465

$0

         Numbers may not total due to rounding